CNC upgrade improves wheel profiling

Retrofitting a wheel lathe with latest CNC brought improved part and tool measurement, tool force monitoring, intelligent machining cycles and a simplified operator interface .

BHP's Iron Ore Division, located at Port Hedland in Western Australia, has one of Australia's largest privately owned rail networks. The 426km single track railroad has built-in passing lanes to accommodate up to 14 trains a day traveling at speeds of 75km an hour in combinations of four to six powerful diesel locomotives and 320 ore cars. For the trains to move over 60 million tonnes of iron ore each year between the company's mines at Newman and the port facility at Port Hedland, BHP must have total confidence in its ability to keep the rolling stock in operation.

Like many Australian companies, BHP Iron Ore is continually seeking to improve performance to better its position as a supplier of high quality iron ore to an increasingly competitive international steel industry.

Safe, low-cost transport of iron ore is an integral part of the company's ability to stay at the forefront of competition.

A key element in the maintenance of the rolling stock is the re-profiling of wheel sets for the ore wagons.

BHP had purchased a custom made Portal Lathe for this purpose in 1992 from Hegenscheidt.

The key factor in the design of this prototype machine was the need for a short cycle time in order to be able to handle the huge volume of wheels required to be machined in BHP's ore car repair shop line.

This original machine control system was a Sinumerik 850T and the manufacturer had spent a number of years to customise the function of the machine to BHP's needs.

After ten years of heavy work, in 2001, CNC Design was approached to retrofit the machine with a new Sinumerik system and to further enhance its capability.

CNC Design is responsible for Sinumerik support in Australia and other SE Asian countries.

Up to six sets of wheel sets are loaded into a magazine.

The operator enters information on the identification and status of the parts.

These are then automatically loaded one at a time into the portal lathe where the wheel profile and back to back are measured.

This data is used to calculate the optimum metal machining cycle to return the profile with minimum metal removal.

The profiles may then be re-measured to check conformance.

CNC Design offered a number of new possibilities including improved part measurement, automatic tool measurement, tool force monitoring, intelligent machining cycles, remote diagnostics and simplified operator interface.

The measured data was to be logged and transferred to BHP's central database.

The project proceeded with the development of a new control system based on the Sinumerik 840D CNC system with 611D digital drives.

CNC Design has previous experience with development of measuring and machining cycles for wheel profiling machines.

This was further developed to meet BHP's specification.

The location, environment and machine availability for the project presented unique issues.

In the Pilbara the temperatures regularly exceed 55 deg C and iron ore dust eventually covers everything.

Port Hedland is located in a remote region more than 4000km from CNC Design's Melbourne office.

The machine was only available for 4-6 weeks for the retrofit.

In short the project had to be conducted under very difficult environmental conditions, in a remote location and in a very short time.

CNC Design's Engineering team fully developed the system software and simulated the operation of the machine.

Valuable input into profile measurement and machining was gained by involvement of the Monash University Centre for Rail Technology, a world leader in wheel life optimisation.

The complete design for the six axis and two spindle system was signed off by BHP before installation commenced.

Due to the location, it was necessary to provide spare parts and all items necessary to the project to site.

Installation of the CNC system and drives and other equipment was completed in two weeks and within four weeks the first wheel sets were machined.

After five weeks the machine was turned over to production.

There have been significant benefits from this project.

Part measurement is faster, more accurate and gives a complete profile instead of descrete points.

The machining is better optimised with significant costs savings due to better wheel usage.

Automation of the tool measurement, tool monitoring and part loading enable the machine to run fully automatically.

BHP are now so pleased with this project that they are planning to further increase productivity by adding a pre-measurement station and integrating the system into their SAP database.

Further reduction in cycle time is expected by the introduction of RF tagging of the wheelsets.

The wheelset ID will be automatically picked up by the Siemens 840 system the Id number will then be varified by SAP.

Finally a file will automatically uploaded to SAP with all pre and post machining details, providing accurate data and reduction in man hours.